This is an update of the activities on the LRO I&T program.:
The spacecraft has been in the EMI/EMC test for 24 hours.
We have completed 6 of the 9 "LOOPS" or test configurations.
We have been attempting to run Loop 7 for the better part of the Saturday evening shift. We have not been successful. We have been experiencing problems with the Ground System Receiver; the CORTEX unit. We have not been able to receive and process the K band, data at the 25 Mbps downlink rate. Earlier we were able to receive and process the K band data at the 100 and 50 Mbps rates. We tried resetting the receiver with little success. The testing was halted at 9:00 PM. Testing will resume on Tuesday 9/2/2008 at 8:00 AM