- Verifying new ITOS release (being installed tonight)
- Load FSW files to EEPROM (new DS destination/filter table and RTS #86)
- Test procedures for Lunar Eclipse, LROC background imaging, Orbiter Sim Background procedure, and spacecraft off
- Install the LEND radiation source and perform LEND Long Functional
Once the above activities are complete, the Launch Day procedure should take approximately 2 hrs after which chamber pump down can start.