This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Friday, October 24, 2008

Pre-Thermal Balance Testing (Continues)

We are continuing our pre-thermal balance testing with Mini-RF activities. We completed the LEND background functional test (TB-05). We should be done with Mini-RF tonight. Pre-Balance activities will continue tomorrow which include:

  • Verifying new ITOS release (being installed tonight)
  • Load FSW files to EEPROM (new DS destination/filter table and RTS #86)
  • Test procedures for Lunar Eclipse, LROC background imaging, Orbiter Sim Background procedure, and spacecraft off
  • Install the LEND radiation source and perform LEND Long Functional

Once the above activities are complete, the Launch Day procedure should take approximately 2 hrs after which chamber pump down can start.