This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Sunday, November 23, 2008

TC-139: LOLA CPT #7 complete @ 8:47pm

This was the last LOLA/LR Test in a long series that started at 11:52am today and lasted until 8:47 pm.

Next up: LAMP Functional (3hrs), DSB Memory Test (4-6 hrs, no instruments powered), Start transition to Ambient, MRF Calibration @~30 degC (3am-5am),

6am Start getting ready for Mission Sim 27 & 17.
8am Start Mission Sim 27 & 17.