This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Friday, December 5, 2008

3rd times a charm.

The plan for our 3rd door closing:

Today: (2 shifts)

Reconfigure the chamber and test fixture.
Finish blanket closeouts.
Run SAS Range of Motion.
Run Diviner Self Portrait Scan
Upload WAC Init file and checkout.


Sat. 12/6: Start 3 shift operations.
Start 7am
7a-9a: Orbiter Trending.
9a-10a: LROC NAC Images
10a – 11a: Install LEND radiation source.
11a-12p: Close Chamber Door
11a – 2p: Run LEND Short Functional w/source
2p -3p: Power down Spacecraft
2p : Start Pumpdown
10p: When we get to 5x10^ -5,
Power up spacecraft
Flood shroud.