This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.

LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.

This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Wednesday, July 8, 2009

7 and 7!!!


Above is the STK image of LRO on DOY 189

Today we completed LAMP Activation Phase 1a. The LAMP team reports that they are “happy.” We set DLRE temperature set points to their requested values, the DLRE team reports that they are “happy, happy.” We also activated Mini-RF and they are “happy” as well.

The LRO Spacecraft continues to make the Ops and Engineering Teams "happy" too :-)

As of July 8, 2009, LRO has successfully turned-on all 7 instruments in its Payload Complement: CRaTER, LEND, LROC, LOLA, LAMP, DLRE and Mini-RF!!

Congratulations everyone!!