This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Tuesday, November 11, 2008

Between the tests

Yesterday (Monday) the ST#1 EEPROM was dumped. RF cables were calibrated and installed.

So far today: The SAS harness is installed to the test fixture (playhouse). We powered up and loaded FSW version 4.3.3. We are currently running the C&DH FSW functional.

The plan for the rest of today:
continue C&DH FSW functional
start GN&C FSW functional
at 7:30PM (done or not) we will dump the ST#1 EEPROM (third time) to verify findings.
at 2:00AM we will (in conjunction with Galileo) review the dump and may reload the EEPROM.

that's the plan, I think.