Not the most productive day. We struggled through the GN&C FSW Functional because we had the safing enabled when last time we ran this, the safing was not enabled. We've decided to have Bruce rewrite his procs to take the safing into account and verify them on FlatSat. We will find another time to run this test after the procs have been modified.
For the rest of the evening, we will run the FSW Stress Test and then run Trending.
Tomorrow morning, we will resume with the schedule outlined earlier today.
This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
Wednesday, November 12, 2008
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment