This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.

LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.

This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Sunday, December 14, 2008

Status 12/14 @ 3:40pm

We are still working our way through the Orbiter Functional. Right now we are running the S-band Comm Check. Projected completion of the test is about 6pm.

That means that MRF Calibration should start around 7:30pm.

Configuration for MR #1 starts around 9:30pm

Start of MR #1 should happen around 12:30am