We are still running the Mini-RF Cal Activity which was inserted into the schedule.
10:00 pm ET Start Time -> 11:36 pm ET Completion Time
Started Transition to Hot Soak #4 (TC-196)
11:00 pm ET Start Time
Once the Mini-RF Cal activity is complete, we will configure for Mission Rehearsal (TC-197).
11:45 pm ET Start Time -> 12:25 am ET Completion Time
Mission Rehearsal will commence after that (TC-198) and will run for 24 hrs per the SER for MR1 Rev D.
~12:45 am ET Start Time
Josh
This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
Sunday, December 14, 2008
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment