This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Thursday, January 8, 2009

Ka-band functional underway

The S-band functional ran from 12:15 until 5:30AM. Adan was nice enough to end his vacation by getting off the plane, driving here, and running a very successful test. The plan for the rest of the day looks like this:

6:00AM - 2:00PM Ka-band Functional
2:00PM - 3:00PM Trending #7
3:00PM - 10:00PM Integrated Payload Functional
10:00PM - late MRF source horn + free radiating tests