This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Wednesday, January 7, 2009

Orbiter Trending #6 Complete, S-Band Functional up next

The "trend" tonight is that the tests all went so smoothly they took less time than allocated. Orbiter Trending #6 complete as of 23:00 EST.

S-Band Functional up next at 2:00 AM. Based on allocated/estimated test times, that puts test times predicted as:

Ka-Comm Functional: 8:00
Orbiter Trending #7: 16:00
Payload Functional: 17:00
MRF Source Horn/ Free Radiating Test: 23:00

Note: No Mini-RF turn-on in Payload Functional cuts test time down to 6 hours

MRF team - if the S/Ka Functionals take less than the 14 hours total allocated, we'll be able to start sooner than 23:00.