This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Thursday, November 20, 2008

More Predictions…

The LEND Functional (TC-45) has just completed ahead of schedule and the anticipated LROC testing is temporarily on hold awaiting thermal conditions to just be right. The thermal team believes that this might take up to two hours?

Following this is some SSR management and the Orbiter Trending (TC-52).

The Mini-RF Calibration Activity (TC-54) is expected to commence around midnight once the battery is up to 33.6 and instrument support will be on hand.