This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.

LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.

This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Friday, November 21, 2008

TC-54 complete

TC-54 (Mini-RF calibration) has been completed. The next two steps TC-55 and TC-56 (collectively referred to as the Mini-RF CPT) have begun.

We have completed most of TC-58 (Propulsion Catbed Test) except for adjusting the battery voltage down to 32V.

We are still expecting to be done all Cold Soak activities by 8AM.

Early morning cheerfulness can be extremely obnoxious. William Feather (1908 - 1976)