This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Sunday, November 16, 2008

We are currently performing lro_comm_03.proc of the Orbiter Functional

We are performing the lro_comm_04.proc
Going by the timeline, we have completed 10 hours of the 20 hour long Orbiter Functional Test. At this rate, we will not complete the orbiter Functional Test before 6:00 AM tomorrow morning.