This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Friday, November 21, 2008

Status 11/21 @1:15pm

TC-59: Cold Soak was completed by 8am.
TC-62: Orbiter Trending was run from 9am to 10:50am.
TC-65: FSW Controlled Heater Functional was run from 11am-1p.
TC-66: RWA Spin Down Test started at 1p.

Changes to the plan:
Keep running the LROC B/G Images until 8pm.
Stop LROC B/G Images (TC-67)
Start TC-68, MOC Flight Procedure Checkout from 8p-12a.
Restart LROC B/G Images at 12a and run until we reach Hot Soak.

About Sim 27 & 17, we are going to try and time it so we start the sim at 8am on Monday 11/24.
Keep an eye on the blog.