To recap, the Payload Functional ran from 9:50a-4:45 pm. We ran TC-73, 74, & 75 before the Payload Functional.
Not going to run the CSS Functional at this time. Forgot we need the loop backs in so we need to configure for it during the break.
Next up: We will run the RWA spin down test, take more LROC background images, then go into the CRaTER functional.
"Experience is the name every one gives to their mistakes."
Oscar Wilde ('Lady Windemere's Fan' 1892)
This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
Saturday, November 22, 2008
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment