Yesterday we completed the FSW load and the C&DH FSW Functional. We also dumped the ST1 EEPROM and uploaded a correction to the two corrupted words. ST1 was rebooted and it seems to be operating nominally now. Hurray!
Today we have installed an ITOS patch to correct some bugs and allows everyone to monitor GDS telemetry. Currently, we are running the GN&C FSW functional. After that, the plan is to run the FSW Stress test and then orbiter trending. We think this will take the rest of the day.
Tomorrow (11/13) the plan is:
LEND functional - no source. (8a-11a)
LROC Collimator Test. (11a-3p)
Install LEND radiation source. (3p-3:30p)
Close Chamber Door (4p-5p)
Run MRF Calibration & Amplitude tests (3p-5p)
Run LEND test - with source (5p-9p)
Run LOLA and LR CPT series. (9p-2a)
Run LOLA part of the Payload Functional (2a-4a)
Friday (11/14);
Start Launch Day Proc (5a-7a)
7a Configure for Pump Down
8a Start Pump Down.