We will start the Orbiter Functional for CPT-2 on Friday, Jan 2 at 8:00am.


The man who comes back through the Door in the Wall will never be quite the same as the man who went out. He will be wiser but less sure, happier but less self-satisfied, humbler in acknowledging his ignorance yet better equipped to understand...Aldous Huxley, "The Doors of Perception"
Seems as if we have we’ve found some momentum. See attached for cartoon metaphor.
We are still working our way through the Orbiter Functional. Right now we are running the S-band Comm Check. Projected completion of the test is about 6pm.
That means that MRF Calibration should start around 7:30pm.
Configuration for MR #1 starts around 9:30pm
Start of MR #1 should happen around 12:30am
Run the MRF Hot Soak tests TC-167 thru TC-170.
We are waiting for the SAS to get to hot op balance. Hopefully it will be there when we finish the MRF testing.
After SAS is at balance, drive the ITP to Hot Soak temps.
Once ITP is at Hot Soak temps, run Ka functional (8hr) and then the S-band functional (6 hrs)
In parallel, we are waiting for LEND to get to Hot op balance, maybe around midnight?
Once LEND gets to balance, we will configure the chamber for Hot Soak.
Once LEND gets to hot soak, we can run the instrument testing.
You will note I put no times on anything. ;-) At the bottom of the blog is the updated schedule.
Here’s the status @ 4:15pm.
TC-126 Payload Functional 2:32a-9:25a
Dump SSR 9:25a-11a
TC-127 LAMP Functional 11a-12:03p
Star Tracker EEPROM Dump 12:06p -12:30p
TC-128 DLRE Functional 12:38p – 1:42p
TC-119 LOLA CPT # 7 1:58p – 4:09p
Note: The sim is earlier than on previous versions of the schedule because there's a 24 hour wait at the beginning of the transition. In reality, the whole transitions takes about 24 hours. As soon as we configure for transition we will begin Sim #30. There is a plan to move the MRF calibration to before the transition configuration. Sorry for the confusion.
We are currently in TC-126; Payload Integration Functional.
We have completed:
TC-118; LOLA CPT#4, Started 10:50pm, completed 11:00pm on 12-08-08
TC-119; LOLA CPT#7, Differed to end of cold soak
TC-120; LR CPT#1, Started 11:00pm, completed 11:15pm on 12-08-08
TC-121; LR CPT#2, Started 11:15pm, completed 11:30pm on 12-08-08
TC-122; LR CPT#3, Started 11:30pm, completed 11:45pm on 12-08-08
TC-123; LR CPT#4, Started 11:45pm, completed 11:51pm on 12-08-08
TC-124; LR CPT#5, Started 11:55pm, 12-08-08, completed 12:00 on 12-09-08
TC-115; LOLA CPT#9 Rerun, Started 12:10am, completed 01:05an on 12-09-08
TC-125; Dump SSR Recorder, Started 01:17am, completed 02:28am on 12-09-08
TC-126; Payload Integration Functional, Started 02:32am
Curtis Dunsmore
We are currently in TC-118; LOLA CPT #4.
6:40 p.m. TC-108; Orbiter Trending
6:50 p.m. TC-109; LROC Collimator (Soak)
6:55 p.m. TC-110; LROC B/G Imaging (Fill Images)
7:30 p.m. TC-111; LOLA Functional
8:40 p.m. TC-112; LOLA CPT #9
9:25 p.m. TC-113; LOLA CPT #5
10:15 p.m. TC-114; LOLA CPT_CAL
10:40 p.m. TC-116; LOLA CPT #2
10:50 p.m. TC-117; LOLA CPT #3
LOLA CPT #1 and #7 are differed to the end of the soak.
Next We’ll continue with LR CPT testing
Massoud
Sat. 12/6: Start 3 shift operations.
Start 7am
7a-9a: Orbiter Trending.
9a-10a: LROC NAC Images
10a – 11a: Install LEND radiation source.
11a-12p: Close Chamber Door
11a – 2p: Run LEND Short Functional w/source
2p -3p: Power down Spacecraft
2p : Start Pumpdown
10p: When we get to 5x10^ -5,
Power up spacecraft
Flood shroud.
We are making progress through our list of activities. We have completed the LEND test without the source and the LROC collimator test. We are currently checking out the new RF switch box. At 1pm we will remove the LOLA CDA purge, install the LEND source and close the door. After door closure, we will run the LEND test and then the MRF tests.
We started to backfill the chamber at 1:00 today. We should be ready to open the door around 4pm.
- 4pm -5p: Radiation Safety enters chamber to remove source/take sample & let us know we are clear to enter the chamber.