This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Friday, November 7, 2008

Current Plans for tonight.

We started to backfill the chamber at 1:00 today. We should be ready to open the door around 4pm.

- 4pm -5p: Radiation Safety enters chamber to remove source/take sample & let us know we are clear to enter the chamber.

- 5p: Chamber & Blanket folks go in to remove enclosure panels.

- Contamination removes witness plates

- Blanket folks make access for installation of the LVA cold ring and access to the Connector Test Panel.

- Mechanical and /or Chamber folks install +X and –X cat walks. (around 7p???)

- Mechanical to remove Test connector panel cover.

- Electrical folks to help prop test NSIs

- Electrical folks to configure test connector panel.

- Battery GSE STM.

- Chamber folks to remove TCs at –X end.

- SAS Gimbal blanket mods start