This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
Saturday, October 25, 2008
T-Vac Status - 10/25/08 @9:10pm
We completed taking a series of LROC WAC images for the LROC team. We moved onto the Lunar Eclipse Test procedure, currently ~%50 done. We plan to run some LROC background image procedures later and power down for the evening.
Status - 10/25/08 @8pm
We completed LEND functional with radiation source. We attempted to load the ITOS patch, but there were problems with the new version with telemetry distribution. We reverted back to the previous release. We plan to load the new version during the chamber break.
We are currently running LROC WAC images and will move onto the Lunar Eclipse proc shortly.
We are currently running LROC WAC images and will move onto the Lunar Eclipse proc shortly.
T-Vac Status 10.25.08 7:35pm
We are on-track for running the Launch Day Procedure (TB-14) at 7am tomorrow with chamber pump down (TB-15) predicted for 9am. Currently we are completing the LROC background checks and expect to finish up this evening by 11pm.
Status 10/25 @3:45pm
We have completed the fixes to the test heater circuits and have placed the LEND test radiation source in the chamber. The chamber door is closed!!!
We have completed the DS filter table load and successfully retested RTS 86. Currently, we are running the LEND long functional test. After the LEND test, we will complete the dry run of the LROC background procs. We did one of the six already. We also need to run the Lunar Eclipse, and the emergency power off procs.
I think we are good for tomorrow morning.
We have completed the DS filter table load and successfully retested RTS 86. Currently, we are running the LEND long functional test. After the LEND test, we will complete the dry run of the LROC background procs. We did one of the six already. We also need to run the Lunar Eclipse, and the emergency power off procs.
I think we are good for tomorrow morning.
Pre-Pump Down Status
Despite my hopes to get to pump down today, Dave and I determined we would not make an 8pm pump down tonight. We had some hiccups getting started this morning after compiling the database.
Also, the chamber folks are troubleshooting a harness heater.
Plan for today is to wait for the chamber folks to fix the heater problem, install the LEND source, run the LEND functional and then verify the LROC collimator has not been disturbed.
In between, we will be dry running the SAS Orbit Cycling proc, LROC background procs, Lunar Eclipse proc, and loading the DS table & RTS 86 update. Also need to install an ITOS patch. We will run into 3rd shift if we have to, to complete these activities. Phil, call Rick on 2nd to see if you need to come in.
Sunday morning at 7am, we will begin with the Launch Day Procedure (2hrs) and then begin pump down (around 9am).
So far today, we have updated the database and rerun the Hot Orbit Transient. We have started the load of the DS filter table and RTS 86 update.
Also, the chamber folks are troubleshooting a harness heater.
Plan for today is to wait for the chamber folks to fix the heater problem, install the LEND source, run the LEND functional and then verify the LROC collimator has not been disturbed.
In between, we will be dry running the SAS Orbit Cycling proc, LROC background procs, Lunar Eclipse proc, and loading the DS table & RTS 86 update. Also need to install an ITOS patch. We will run into 3rd shift if we have to, to complete these activities. Phil, call Rick on 2nd to see if you need to come in.
Sunday morning at 7am, we will begin with the Launch Day Procedure (2hrs) and then begin pump down (around 9am).
So far today, we have updated the database and rerun the Hot Orbit Transient. We have started the load of the DS filter table and RTS 86 update.
Friday, October 24, 2008
Pre-Thermal Balance Testing (Continues)
We are continuing our pre-thermal balance testing with Mini-RF activities. We completed the LEND background functional test (TB-05). We should be done with Mini-RF tonight. Pre-Balance activities will continue tomorrow which include:
Once the above activities are complete, the Launch Day procedure should take approximately 2 hrs after which chamber pump down can start.
- Verifying new ITOS release (being installed tonight)
- Load FSW files to EEPROM (new DS destination/filter table and RTS #86)
- Test procedures for Lunar Eclipse, LROC background imaging, Orbiter Sim Background procedure, and spacecraft off
- Install the LEND radiation source and perform LEND Long Functional
Once the above activities are complete, the Launch Day procedure should take approximately 2 hrs after which chamber pump down can start.
more pre-TB testing
This morning we have performed some more fun pre-testing with:
LROC collimator (TB-03) , to determine that it's in the right place and pointed in the right direction, we took some really cool NAC images.
We also inadvertently power-cycled the lead TC workstation, which has some really interesting effects. This activity has not been assigned a TB number.
We have finally run the DLRE soak scan (TB-02) cleanly all the way through.
We have started executing the LOLA / LR CPT (TB-06).
We are still shooting for door closure on Saturday at 2PM.
LROC collimator (TB-03) , to determine that it's in the right place and pointed in the right direction, we took some really cool NAC images.
We also inadvertently power-cycled the lead TC workstation, which has some really interesting effects. This activity has not been assigned a TB number.
We have finally run the DLRE soak scan (TB-02) cleanly all the way through.
We have started executing the LOLA / LR CPT (TB-06).
We are still shooting for door closure on Saturday at 2PM.
Thursday, October 23, 2008
Pre-pumpdown setup and proc checks continuing
TVac test preparations inside the SES chamber are going well. Today the thermal team finished the blanketing, and facilities engineers ran the LN2 plumbing and completed leak check. Fri 10/24 they hope to complete heater and thermocouple checkout and be ready for a Saturday evening pumpdown.
Outside the the chamber, powered testing and proc checkouts consisted of:
*Hot Transient Simulation Proc Dry Run
*LROC WAC Firmware update
*Cold Start Proc Dry Run
*High voltage "emergency off" Proc Dry Run
*Lunar Eclipse Simulation Proc Dry Run
Wednesday, October 22, 2008
Payload Integrated Functional Dry Run complete
Payload Integrated Function dry-run tonight was successful. This is one of the most intricate procs we will ever run on the orbiter and to have it run as cleanly as it did was pretty impressive. Kudos to Jeff, Tim and the others who helped develop it.
Getting Ready for TVac: Wed 10/22
Status 10/22: Today we completed blankets that go inside the enclosure. Removed the scaffolding outside the enclosure. Placed RF, MRF, and LR cables inside the "dog house". Removed instrument, star tracker and thruster covers. Ran memory scrub test on C&DH. Currently, dry running the Integrated Payload Functional.
Tomorrow we install the rest of the enclosure panels and hook up cryo lines. Continue to test thermocouple and test heaters. Install test blankets outside the enclosure.
I see the light (or in this case the door) at the end of the tunnel.
Tomorrow we install the rest of the enclosure panels and hook up cryo lines. Continue to test thermocouple and test heaters. Install test blankets outside the enclosure.
I see the light (or in this case the door) at the end of the tunnel.
Tuesday, October 21, 2008
Instrument pre-pumpdown proc checkouts continue
After successfully running the DLRE Field-of-Regard scan, systems/ops performed a special lights-out test for the LROC WAC and ran a series of short configuration procs for CRaTER and LEND.
Current plan will be to run the Payload Integrated Functional starting Wednesday early afternoon
Chandrayaan launched!
Congratulations to ISRO's Chandrayaan mission which has just been launched! Best of luck for a successful mission! We'll meet you at the Moon in a few months.
TB-02 Dry Run Completed For Diviner
Diviner field of regard test now ongoing (spacecraft self-portrait) ongoing. Plan is to run CDH DSB test tomorrow morning (~9am) followed by Integrated Instrument Functional dry run.
Getting Ready for TVac: Tues 10/21
Status 10/21: Good day today. Installed the two end +Z test panels. Installed the test enclosure. Removed the HGAS bag and the upper spacecraft bag. Secured the SAS gimbal harness to the enclosure. Starting installation and checkout of the test enclosure thermocouples, heaters and test blankets. We are performing a dry run of the Integrated Payload Functional this evening.
Monday, October 20, 2008
Getting Ready for TVac: Mon 10/20
Status 10/20: We continue to install and test thermocouples and heaters today. We are also dry running some procs. We hope to install the enclosure Tuesday morning. After the enclosure is installed and the contamination bags are removed, we will dry run the Integrated Payload Functional. If things go well, we hope to get to the dry run right after lunch.
Sunday, October 19, 2008
T-Vac Update: LROC Data Flow Problem Overcome!
WOA-02185 was successfully completed with 12 hours of LRO/LROC operation with no LROC data loss or interruptions. This verified the FSW patch works.
The test is being followed by a LROC WAC test "lr-testwac.proc" run at various exposure settings per LROC request as the opportunity presented itself to do this this evening.
T-Vac instrumentation work continued through the evening with completion projected for late tomorrow at the earliest.
The test is being followed by a LROC WAC test "lr-testwac.proc" run at various exposure settings per LROC request as the opportunity presented itself to do this this evening.
T-Vac instrumentation work continued through the evening with completion projected for late tomorrow at the earliest.
Test Enclosure Installation NET Monday Evening.
We don't think the instrumentation/heater check out will be done today. Latest estimates take us to Monday at the end of first shift (4p-5p).
FSW patch 4.3.2.1
We have struggled through power-up and installed the FSW patch 4.3.2.1. Now we are endeavoring to configure the spacecraft for the 12-hour loop. I'm glad that Mike Blau is here.