This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Friday, October 24, 2008

more pre-TB testing

This morning we have performed some more fun pre-testing with:

LROC collimator (TB-03) , to determine that it's in the right place and pointed in the right direction, we took some really cool NAC images.

We also inadvertently power-cycled the lead TC workstation, which has some really interesting effects. This activity has not been assigned a TB number.

We have finally run the DLRE soak scan (TB-02) cleanly all the way through.

We have started executing the LOLA / LR CPT (TB-06).

We are still shooting for door closure on Saturday at 2PM.