This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.

LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.

This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Monday, November 24, 2008

Sim 17 started

Sim 17 started at 2140. SIM 17 will be approximately 5 hours in duration . At 3.5 hous into the SIM The Insertion Burn will be preformed.


Some mornings it just doesn't seem worth it to gnaw through the leather straps.
- Emo Phillips

SIM 27 Complete

Sim 27 completed at 19:40. At this time we are configuring for SIM 17 which will simulate LOI-1 Maneuver and perform early mission activities.

"I try to take one day at a time, but sometimes several days attack me at once"

3rd time is the charm Sim-27

Sim-27 started at ~1400 and is scheduled to run for 6 hours. GDS had a problem with the RW‘s and the current problem is the timing between GDS writes and FSW reads. The current problem as of this writing is not a show stopper. The timing is being tweaked as the simulation moves forward.



"What if everything is an illusion and nothing exists? In that case, I definitely overpaid for my carpet"

Sunday, November 23, 2008

TC-145: LAMP Functional Complete

TC-145: LAMP Functional 8:49-10:30pm
Ran 2 NAC images @ 10:32p & 10:35p
TC-83: Turn off instruments. 10:37p-10:44p
TC-84: Dump SSR Recorder. 10:46p
Power down Ka system @ 11:14p
TC-85: C&DH DSB Memory Test. Started @11:16p

"Nothing fixes a thing so intensely in the memory as the wish to forget it." -Michel de Montaigne



TC-139: LOLA CPT #7 complete @ 8:47pm

This was the last LOLA/LR Test in a long series that started at 11:52am today and lasted until 8:47 pm.

Next up: LAMP Functional (3hrs), DSB Memory Test (4-6 hrs, no instruments powered), Start transition to Ambient, MRF Calibration @~30 degC (3am-5am),

6am Start getting ready for Mission Sim 27 & 17.
8am Start Mission Sim 27 & 17.

"Engineering is the art of modeling materials we do not wholly understand, into shapes we cannot precisely analyze so as to withstand forces we cannot properly assess, in such a way that the public has no reason to suspect the extent of our ignorance." - Dr AR Dykes -

TC-130 to 144: LOLA and LR Testing as of 8:40pm

TC-140: LR CPT #1 2:36 pm - 3:00 pm
TC-141: LR CPT #2 3:01 pm - 3:11 pm
TC-142: LR CPT #3 3:12 pm - 3:19 pm
TC- 143: LR CPT #4 3:21 pm - 3:28 pm
TC-144: LR CPT #5 3:28 pm - 3:40 pm
TC - 131: LOLA CPT #9 3:44 pm - 4:01 pm
TC-132: LOLA CPT #5 Skipped this because it is very close to LOLA CPT #5 FSW
TC-133: LOLA CPT #5 FSW: 4:30pm - 5:09 pm
TC-134: LOLA CPT Cal: 5:10 pm- 6:02pm
TC-139: LOLA CPT #7: Started at 6:05 should end around 9pm



"...new torments and new tormented souls I see around me wherever I move, and howsoever I turn, and wherever I gaze." - Dante's Divine Comedy (third circle)

Full Speed Ahead

The LOLA Functional (TC-130) was completed at 12:34pm. And from there we moved into the LOLA CPT’s (slightly out of order from the suggest handout).
LOLA CPT #1 (TC-135) started at 12:44pm and was completed at 1:40pm.
LOLA CPT #2 (TC-136) started at 1:41pm and was completed at 1:54pm.
LOLA CPT #3 (TC-137) started at 1:55pm and was completed at 2:11pm.
LOLA CPT #4 (TC-138) started at 2:11pm and was completed at 2:35pm.
LR CPT #1 (TC-140) started at 2:36pm and is under way.

Mid Day Update on a Beautiful Sunday Afternoon

The Orbiter Trending (TC-82) which was started at 7:10am wrapped up at 8:45am.

In anticipation of instrument testing, the LEND instrument was then turned on and configured from 9:00 to 9:10am. This was immediately followed without delay by configuring the LOLA instrument to begin firing it’s laser.

After a cup of coffee and a little warm up time, we began the LEND Functional (TC-80) at 10:10am. This functional was completed at 11:40am followed by retrieval of the data for the instrument team.

Now it is time for the LOLA show. We have just started the LOLA Functional (TC-130) at 11:52am and this is expected to run for about an hour. Following this is then about 8 hours or so of LOLA and LR CPT’s.