This blog follows the progress of the LRO mission through Integration and Testing at NASA's Goddard Space Flight Center and launch site processing at KSC\Astrotech. Its purpose is to enable communication to the entire LRO Team about the status of ongoing activities.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
LRO was launched June 18th, 2009 at 5:32pm EDT from KSC. This BLOG will follow the progress of the mission as LRO travels to the Moon and establishes orbit around it.
This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.
Saturday, December 13, 2008
The Payload Combined Functional Test, TC-186 will be complete by 9:30 PM
The Payload Combined Functional Test, TC-186, which started at 2:15 PM today will be complete by 9:30 PM. At which time we will re-configure for and collect the LROC images, TC-187 through TC-190. We will then dump the SSR, TC-191. These tasks should take us until 11:00 PM. At that point we will perform, TC-192, Reconfigure for the Orbiter Functional Test. The Orbiter Functional Test, TC-193, should start between 11:30 PM, tonight, 12/14/2008 and midnight.
TC-186 Payload integrated Funcition Start
TC-186 Payload Functional Started 1:30pm
LN_ powerup
LOLA switched to laser 2
S-band tx on
ka mod off
imu on
RWA on 0 torque
hg gce on
all instruments on
Thermal comfig F
Last night I lay in bed looking up at the stars in the sky and I thought to myself, where the heck is the ceiling.
LN_ powerup
LOLA switched to laser 2
S-band tx on
ka mod off
imu on
RWA on 0 torque
hg gce on
all instruments on
Thermal comfig F
Last night I lay in bed looking up at the stars in the sky and I thought to myself, where the heck is the ceiling.
Payload Functional moved up to 13:00 EST
We will have a quorum there from Payload to start the Payload Functional by 13:00, which moves the schedule to the left by 14 hours against the schedule posted below.
Note that this moves the start of the orbiter functional up to approx. 22:00 EST tonight
Arlin has spoken
Arlin has been notified and the Payload functional will begin as planned
TC-186 Payload Integrated Functional will begin at 3:00 pm today.
TC-186 Payload Integrated Functional will begin at 3:00 pm today.
Charles would have a better chance of guessing your weight
Charles says you shouldn't trust anything he says.
He has proclaimed soak. Only four hours early.
So TC-185 is complete at 1015
ready to start TC-186 Payload Functional but no one from payloads is here.
We are calling Arlin to see we can start.
The man who smiles when things go wrong has thought of someone to blame it on. - Robert Bloch
He has proclaimed soak. Only four hours early.
So TC-185 is complete at 1015
ready to start TC-186 Payload Functional but no one from payloads is here.
We are calling Arlin to see we can start.
The man who smiles when things go wrong has thought of someone to blame it on. - Robert Bloch
Trying to soak it all in
TC-180, DLRE Field of Regard Thermal Mapping, completed at 0630
TC-182 and 184 LROC B/G Imaging still running in background
TC-186 Payload integrated Functional will be starting 1400-1500
This one's for Kevin
There is a fine line between fishing and just standing on the shore like an idiot.
TC-182 and 184 LROC B/G Imaging still running in background
TC-186 Payload integrated Functional will be starting 1400-1500
This one's for Kevin
There is a fine line between fishing and just standing on the shore like an idiot.
Make Your Saturday Plans with LRO
TC-179, Configure Instruments, completed at 12:44 am.
TC-180, DLRE Field of Regard Thermal Mapping, which runs in parallel with other activities, was started at 12:45 am.
TC-181 and TC-182, LROC B/G Imaging, procedures were started at 12:52 am will continue to run in the background.
At 12:55 am, the RW Torque Override Commanded was sent to command all the torques to zero. This was done at the request of thermal to help cool down the spacecraft a little faster.
And we continue on our path to Cold Soak #4. The Orbiter should be in cold soak conditions just in time for brunch.
My magic eight ball is also telling me that the Payload Functional, TC-186, will be executed later today around 3:00 pm.
TC-180, DLRE Field of Regard Thermal Mapping, which runs in parallel with other activities, was started at 12:45 am.
TC-181 and TC-182, LROC B/G Imaging, procedures were started at 12:52 am will continue to run in the background.
At 12:55 am, the RW Torque Override Commanded was sent to command all the torques to zero. This was done at the request of thermal to help cool down the spacecraft a little faster.
And we continue on our path to Cold Soak #4. The Orbiter should be in cold soak conditions just in time for brunch.
My magic eight ball is also telling me that the Payload Functional, TC-186, will be executed later today around 3:00 pm.
Friday, December 12, 2008
MOC Procedure Testing will end around 11:00 PM
The MOC procedure Test, TC-178, will continue until 11:00 PM (+/-) a few minutes. Then we will configure the instruments per TC-179 and start the DIVINER Thermal Mapping, TC-180, and LROC imaging TC-182,& 183 (both in the background), while the Mini-RF, TC-182 tests will take center stage.