This BLOG will be periodically updated during LRO's early mission but as the nominal mission unfolds the official NASA LRO website and the LRO Science Instrument's own websites will evolve into a more interesting sources of LRO science results as postings appear there first and LRO engineering and operations (source of this site) will become increasingly routine.




Tuesday, October 14, 2008

Getting Ready for TVac: Tues 10/14

Status 10/14: Rotated SC -Y down. Installed heaters and TC to HGAS hat coupler. Reinstalled hat coupler. Installed HGAS lift bar. Routed RF & LR cables down boom. Installed LR shower head. Installed MRF short cable & closed blanket. Removed thermal test enclosure from chamber. Installed GSE cables in chamber. Installed bottom sled bracket to orbiter. Installed GDS SW version 1.10a. Blanketed CSS harness.

2 comments:

Joanne said...

As of 6:30p: Still some blanketing yet to do. Walkdown at 8:30am

AMMR said...

Great!! First time to use the site and the scam cam in the white room doesn't work!! Where's QA when you need them!!